Confirmation of verbal instruction
Construction contracts generally give the contract administrator the power to issue instructions to the contractor.
Broadly, instructions may be given:
- To vary the works
- To postpone the works.
- To remedy workmanship, goods or materials, and equipment which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
The contractor must comply with the instructions within certain limitations. They have the right to ‘reasonably object’ to an instruction, and instructions can only be given as empowered by the contract.
Generally, instructions must be made formally, in writing, following a procedure set out in the contract. However, it is common for contracts to allow instructions to be given verbally, for example during a meeting, a site visit, or in an emergency situation. In this case, either the contract administrator should then confirm the instruction in writing to the contractor, or the contractor should confirm the instruction in writing to the contract administrator. If the receiving party does not dissent from the written confirmation, then the instruction will take effect.
This confirmation is referred to as a confirmation of verbal instruction (CVI) or an oral confirmation sheet. The contract should set out the exact procedures and the timescales for issuing such an instruction and dissenting from it.
Contracts can be vague about the nature of such confirmations, other than that they should be given in writing. Generally they should include:
- Details of who it is issued by and who it issued to.
- The date.
- Details of the contract that permits the instruction.
- The number of the CVI.
- Details of the instruction.
- The signature of the party issuing the CVI.
It is sensible to send an instruction by recorded delivery, or to confirm its receipt in the minutes of subsequent meetings. On some projects, there may an automated system in place for capturing and managing CVI’s and other instructions.
If a formal procedure is not followed for confirming verbal instruction, there can be disputes about:
- Work that has not been done which the contract administrator believes have been agreed.
- Work that the contractor has done but the client does not wish to pay for.
- Whether the instruction has been given to the right person, by the right person.
- Whether the instruction is allowed under the contract.
- Whether it has been properly valued and the value agreed.
- Whether the consequences on the programme have been properly considered.
- Whether an extension of time should be awarded.
Some contracts may make it a condition precedent to works being carried out that instructions are issued in writing. However, this can put the contractor in a difficult position, and whether to proceed with the works or to wait for a written instruction may be a commercial rather than a legal decision.
It is important that any instruction it is given by the contract administrator, rather than, for example, by the client, otherwise the instruction may constitute a new contract.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Architect.
- Architects instruction
- Change control
- Compensation events.
- Contract administrator.
- Contract sum.
- Defects liability period.
- Defects.
- Extension of time.
- Instruction.
- Mediation.
- Oral variation to written contract.
- Provisional sums.
- Relevant event.
- Variations.
- Work instruction.
Featured articles and news
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.